Fabrication and Installation of New Process Underground Floor Drainage System for Genzyme at their New Bio-Tech Plant, located at GEEL, Belgium.

MSL were appointed mechanical contractor for the supply and installation of the underground process drainage system. The ground floor area level of this new Bio-Tech Plant measured 7,200sq metres, incorporating in excess of 100 no Floor and Channel Gullies for process drainage.

Client: THV Genster
Project Description: Supply & Installation of Underground Process Drainage System.
Contract Value: € 450,000
Contract Duration: 8 Weeks

The key features and project work scope consisted of the following:

  • Generation of Isometrics (150 approx) for the underground process drainage pipe work.
  • Fabrication of pipework (consisting of 4,000 weld inches) at MSL fabrication facility. NDT of 20% and Boroscope performed on welds, achieving a 100% success rate.
  • Shipment of Fabricated Pipe Spools from Cork to GEEL, Belgium.
  • Supply and Fabrication of 100 stainless steel gullies and gully channels for Clean Room process drainage specifications.
  • Supply Civil Contractor with the required trench elevations for the new process drainage.
  • Installation of new process drainage pipe work at Genzyme. This consisted of 750m of schedule 10 stainless steel pipe, size ranging from 4 to 10 inch nominal bore. All pipe work was installed to achieve a 1:100 fall.
  • Installation of all floor gullies and gully channels to the required elevations. (Tolerance Requirement = + / – 2mm)
  • NDT of all field welds.

Direct Labour Hours: A total of 5,000 hours were expended on the project

Talk to MSL Engineering Ltd. today

Contact us at +353 (0) 21 4513550 or email info@mslengineering.ie